Biogas Upgrading System with Bio-Regenerative Scrubbing for High-H₂S STP Gas
The system covers everything from the STP's digesters to the city gas grid, including bio-regenerative H₂S scrubbing, compression, membrane upgrading, metering and odorisation.

The plant is the first Bio-CNG project of VA Tech Wabag (WABAG) and PEAK Sustainability Ventures. It is located at Ghaziabad Nagar Nigam's 70 MLD sewage treatment plant at Dundahera and is developed through their joint venture, Ghaziabad Bioenergy Pvt Ltd, under a build-operate-transfer agreement with the Nagar Nigam. CRA's scope is the complete gas train between the STP's digesters and the city gas grid. The train removes H₂S from the raw digester gas in a chemical scrubber with biological regeneration followed by activated carbon polishing, then compresses and chills the gas, upgrades it to CBG in a membrane system, and meters, odorises and regulates it for injection into the city gas network. It is designed to deliver CBG that meets IS 16087:2025.
Turning Sewage Digester Gas into Grid-Quality CBG
Sewage digester gas reaches the gas train at low pressure, carries high and variable H₂S and is saturated with moisture. Before it can enter a city gas network, it has to meet IS 16087:2025 for methane, H₂S, moisture and oxygen. The main requirements were:
- Remove high and variable H₂S from low-pressure digester gas without adding air to the gas
- Keep H₂S, moisture and oxygen within IS 16087:2025 at the grid connection
- Separate CO₂ while keeping methane losses low
- Fit the train beside the digesters of a working sewage treatment plant
- Meter, odorise and regulate the CBG for the city gas network
One Gas Train from the Digesters to the Grid
CRA designed a single gas train that takes raw digester gas from the STP and delivers CBG to the city gas network. Bulk H₂S removal uses CRA's chemical scrubber with biological regeneration, which regenerates its caustic with bacteria and adds no air to the gas. Activated carbon then polishes the gas before compression and membrane upgrading.
Core components
- Chemical scrubber with biological regeneration, with its bioreactor, settler, aeration blower and recirculation pumps
- Activated carbon polishing vessels
- Gas compression package with aftercooling
- Gas chiller to remove moisture ahead of the membranes
- Membrane system to separate CO₂ from methane
- Online gas analysis
- Metering, odorisation and pressure regulation for grid injection
Engineering and design
- Designed to IS 16087:2025 for CBG quality
- Process, mechanical and electrical design done in-house by CRA
- Configured for high-H₂S sewage digester gas
Designed for Grid-Quality CBG
- Raw biogas capacity of 250 Nm³/hr at peak
- CBG output of about 1.8 tonnes a day
- H₂S below 100 ppm after bulk removal and below 5 ppm after polishing
- Air is kept out of the gas during H₂S removal, so oxygen in the CBG stays within specification
- CBG designed to meet IS 16087:2025 at the grid connection
A Complete CBG Gas Train at a Sewage Treatment Plant
This project brings CRA's gas cleaning and its CBG gas train together at a municipal sewage treatment plant, with one supplier responsible for the whole train from the digester gas inlet to the grid connection. The plant is the first of the 100 sewage-to-CBG plants that WABAG and PEAK plan in India and other markets, and it shows how an STP's digester gas can be cleaned and upgraded into CBG for a city gas network.